PDA

View Full Version : Power generating companies reply



NewsWhore
09-22-2006, 04:00 PM
The power generating companies have been answering some of the questions posed by the Administrator of the Dominican Corporation of State-Owned Electrical Companies (CDEEE), Radhames Segura, and stated that the generators are out of service due to damage on the 69,000-Volt transmission line. Diario Libre reports that separate releases by AES Dominicana, which manages the Andres and Itabo generators and the Haina Generating company, explained that the transmission area is CDEEE property. The generating companies assured that they had informed the Superintendence of Electricity's Coordinating Office about their plants going out of service, and rejected Segura's statement that they had been irresponsible in failing to explain the reasons for the power outages affecting the country.

More... (http://www.dr1.com/index.html#8)